Planning for July 2023
Well, as all my readers are doubtless aware, we had a small disaster at my home: some combination of a groundwater intrusion through the foundation, and a burst pipe, ended up flooding our basement. Since that’s my living quarters, telework location, and creative office . . . yeah, this was a big disruption.
So here’s the critical path for the next few weeks:
- At the moment I’m standing watch while a crew of emergency movers finish clearing out our basement.
- Tomorrow is the 4 July holiday, and we’ll probably be finishing up a few items and hauling out a fair amount of trash.
- We have a crew coming in starting on 5 July to do foundation repair and install a new (and considerably upgraded) drainage system. That’s likely to take up to two weeks, so figure about 19 July to get that done.
- We plan to take the opportunity to replace the water heater. May as well eliminate one possible cause for another water-based disaster in the future. Not likely to take more than a day.
- Then it’s a matter of patching, priming, and painting drywall and replacing the entire carpet. Not likely to take more than a couple days, if we can coordinate the work efficiently.
Best guess, in the last full week in July I’ll be able to call the movers to bring everything back and help us unload the POD in which my entire personal library is now sitting. Of course, then I’ll be faced with the task of unpacking everything . . .
I do have my computer set up in the living room, so I expect to be able to make some progress on the Architect of Worlds layout, do a book review for July as usual, and maybe push a few other items forward. In particular, I suspect I will be able to release a free update for Architect late this month for my patrons.
Circumstances are not exactly conducive to major progress, though, so (unlike most months) I’m not going to set out any specific milestones for July. Look for a Status Report or two as the month moves along.